浙江宁波LNG项目完成全场首台27万m³LNG储罐抗压环吊装任务
责任编辑:cnlng    浏览:161次    时间: 2024-06-05 11:30:59    | 来源:六建风采   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

尊龙凯时·(中国)人生就是搏!尊龙凯时·(中国)人生就是搏!尊龙凯时·(中国)人生就是搏!电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:据悉,抗压环作为LNG储罐罐顶的重量直接承载件,通过焊接与LNG储罐罐顶进行连接,抗压环的焊接质量尤为重要,为保证抗压环对接缝焊接质量,项目部采用对称同步焊接的方法进行施焊的同时,抗压环对接缝之间安装焊缝组对充分利用卡具,对焊缝间隙、错边量、棱角度及垂..

据悉,抗压环作为LNG储罐罐顶的重量直接承载件,通过焊接与LNG储罐罐顶进行连接,抗压环的焊接质量尤为重要,为保证抗压环对接缝焊接质量,项目部采用对称同步焊接的方法进行施焊的同时,抗压环对接缝之间安装焊缝组对充分利用卡具,对焊缝间隙、错边量、棱角度及垂直度进行及时调整,待抗压环半径、垂直度调整合格后进行接焊缝焊接。根据设计文件和图纸,27万m³LNG储罐抗压环共36块,每块抗压环使用4根F型支架作为支撑,单块抗压环重约4t。此次抗压环吊装使用300t轮胎吊和塔吊配合,吊装至距离地面50.8m处安装就位。

为了确保抗压环一次性吊装成功,在兼顾现场安全管理、质量管控及施工效率的同时,坚持“提前谋划、稳扎稳打、协同配合”的工作原则,在抗压环吊装作业前邀请业主、监理、总包EPC联合体等有关单位召开作业推演、安全技术交底及安全风险辨识等会议,对此次吊装作业风险和作业流程进行分析和讨论,制定了抗压环吊装13项检查内容,并明确相关责任人员。吊装过程中,通过对作业人员安全技术质量再交底、吊索具联合交叉检查及施工安全技术质量管理人员旁站指导等措施,确保吊装一次安全就位、安装过程质量受控。

It is reported that the compression ring is a direct bearing part of the weight of the LNG storage tank top, which is connected with the LNG storage tank top through welding. The welding quality of the compression ring is particularly important. In order to ensure the welding quality of the compression ring against the seam, the project department adopts the symmetrical synchronous welding method to weld while installing the weld group between the compression ring against the seam to make full use of the fixture. The weld gap, the amount of wrong edge, the Angle of edge and the verticality should be adjusted in time, and the weld should be welded after the radius and verticality of the compression ring are adjusted. According to the design documents and drawings, there are 36 compression rings in 270,000 m³LNG storage tank, each of which is supported by 4 F-shaped supports, and the weight of a single compression ring is about 4t. The 300t tire crane and tower crane were used for the lifting of the compression ring, which was hoisted to 50.8m from the ground.

In order to ensure the success of the one-time lifting of the pressure ring, while taking into account site safety management, quality control and construction efficiency, adhere to the working principle of "planning in advance, steady and cooperative", and invite the owner, supervisor, EPC consortium and other relevant units to hold meetings on operation inference, safety technology disclosure and safety risk identification before the lifting operation of the pressure ring. The risk and process of the lifting operation are analyzed and discussed, and 13 inspection contents of the lifting of the compressive ring are formulated, and the relevant responsible personnel are clearly defined. During the hoisting process, the safety and technical quality of the operators are re-revealed, the joint cross-inspection of the sling and the side guidance of the construction safety and technical quality management personnel are taken to ensure the safe positioning of the hoisting and the quality control of the installation process.