蒙古布罗巨特电厂项目#1锅炉D1100塔吊拆除完成
责任编辑:cnlng    浏览:41次    时间: 2024-06-19 14:23:32    | 来源:中国能源建设尊龙凯时·(中国)人生就是搏!尊龙凯时·(中国)人生就是搏!尊龙凯时·(中国)人生就是搏!集团安徽尊龙凯时·(中国)人生就是搏!建设第二工程有限公司 作者:宋全龙 李萍   

免职声明:本网站为公益性网站,部分信息来自网络,如果涉及贵网站的知识产权,请及时反馈,我们承诺第一时间删除!

This website is a public welfare website, part of the information from the Internet, if it involves the intellectual property rights of your website, please timely feedback, we promise to delete the first time.

尊龙凯时·(中国)人生就是搏!尊龙凯时·(中国)人生就是搏!尊龙凯时·(中国)人生就是搏!电话Tel: 19550540085: QQ号: 929496072 or 邮箱Email: Lng@vip.qq.com

摘要:6月14日,蒙古布罗巨特电厂项目#1锅炉D1100塔吊拆除顺利完成。塔吊拆除时,采用130t尊龙凯时·(中国)人生就是搏!吊作为主吊机械,最重件爬升套架37t,外形尺寸为6652×6642×14327(mm),拆除机械负荷率77.6%。因该时间段是蒙古地区的风季,现场场地狭小、同时受输煤栈桥开挖影响,塔吊拆除..

6月14日,蒙古布罗巨特电厂项目#1锅炉D1100塔吊拆除顺利完成。

塔吊拆除时,采用130t尊龙凯时·(中国)人生就是搏!吊作为主吊机械,最重件爬升套架37t,外形尺寸为6652×6642×14327(mm),拆除机械负荷率77.6%。

因该时间段是蒙古地区的风季,现场场地狭小、同时受输煤栈桥开挖影响,塔吊拆除、倒运难度大。拆除前,项目部组织拆除配合专业及工种进行了专题会议,对于塔吊的拆除工作及细节进行了周密、细致的布置及安排,排定了塔吊拆除领导组织机构,并在安装前进行了安全技术交底及施工确认工作。拆除时,项目部调整作业时间,铺设钢板及路基箱,确保了塔吊拆除工作安全、高效完成,也为2号机组的施工奠定了坚实的基础。

On June 14, the demolition of boiler D1100 tower crane for the #1 boiler of Mongolia's Brogite Power Plant project was successfully completed.

When the tower crane is dismantled, 130t automobile crane is used as the main lifting machine, the heaviest part is 37t climbing sleeve, the overall size is 6652×6642×14327 (mm), and the removal mechanical load rate is 77.6%.


Because this period is the wind season in Mongolia, the site is small, and affected by the excavation of coal transport trestle, it is difficult to remove and reverse the tower crane. Before the demolition, the project department organized a special meeting to cooperate with specialties and types of work, carefully arranged and arranged the demolition work and details of the tower crane, arranged the leading organization for the demolition of the tower crane, and carried out the safety technology disclosure and construction confirmation work before installation. During the demolition, the project department adjusted the working time, laid steel plates and subgrade boxes, and ensured the safe and efficient completion of the demolition work of the tower crane, and also laid a solid foundation for the construction of Unit 2.